The latest position of implementation is as follows:
· Primary Data Centre has started functioning at Navi Mumbai since 3rd April, 2013.
· Disaster Recovery Centre has been powered on at Mysore on 15-05-15.
· 28014 Departmental Post offices including mail offices and administrative offices have been networked at single Wide Area Network (WAN) and connected to Data Centre.
· Core Banking Solution (CBS) has been rolled out in 20494 Post Offices.
· ATMs have been installed in 759 locations.
· Core Insurance solution (CIS-PLI) has been rolled out in 25406 Post Offices.
· CSI Wave-1: Implementation of IDAM (Identity and Access Management) and SSO (Single Sign on) are under progress in Mysore Division.
· Other Wave-1 security components are at Data Centre level and they are under implementation.
· Anti-virus installed in 74,500 desktops
Enterprise Monitoring System under CSI Wave-1 is a Data Centre level component and it is under implementation.
Enterprise Monitoring System under CSI Wave-1 is a Data Centre level component and it is under implementation.
· CSI wave 2 Roll out: CSI has been rolled out In Mysore Division from 01.10.2015.
· Two HOs and Sixty three SOs were migrated to CSI in addition to NSH Mysore.
· The following Legacy applications were integrated with CSI.
eMO
eMO ePayment
Register net/ Parcel net
Speed net
IPS
IFS
RMFS
NPS
UAT for Wave 2 & 3 solutions is in progress (Cycle 1 & 2 completed).
· CSI Integration UAT III completed from 22-06-2015 to 27-06-2015 at Hyderabad.
· Closure of defects of UAT III completed from 09th to 11th July 2015 at Hyderabad.
Dispatch of RH Handheld devices started.
· 3546 devices have been dispatched to Branch Post Offices of Pilot circles.